top of page
Concrete Wall

3PI INTEGRATED SYSTEM TESTING

On completion of all individual systems commissioning.Proving of installed system redundancies.

Required Systems (MV; LV; Generator; UPS; Chiller; BMS; PA; Access Control etc).

 

•Building shutdown & Start-up.

•Utility power failure - generator operational.

•Fire Alarm System test on generator power.

•Utility power reinstatement.

•UPS failures.

•Tier failure: Utility power + UPS failure.

•CHW Pump failures;

•Condenser Water Pump failures.

•Chiller failure/s;

•PAC unit duty failures.

•FCU System duty failures.

enquiry@3rdpartyinternational.com

  • LinkedIn

3PI

www.3rdpartyinternational.com

Level 6 & 7 Residensi Tribeca No.215 Jalan Imbi, 55100
Kuala Lumpur, Malaysia

bottom of page