3PI INTEGRATED SYSTEM TESTING
On completion of all individual systems commissioning.Proving of installed system redundancies.
Required Systems (MV; LV; Generator; UPS; Chiller; BMS; PA; Access Control etc).
•Building shutdown & Start-up.
•Utility power failure - generator operational.
•Fire Alarm System test on generator power.
•Utility power reinstatement.
•UPS failures.
•Tier failure: Utility power + UPS failure.
•CHW Pump failures;
•Condenser Water Pump failures.
•Chiller failure/s;
•PAC unit duty failures.
•FCU System duty failures.